Final steam generator lift for Bruce Power's Unit 6 MCR, done safely and event-free

Bruce Power communicationsBy: Bruce Power communications  December 20, 2021
Final steam generator lift for Bruce Power's Unit 6 MCR, done safely and event-free
Bruce Power’s Unit 6 Major Component Replacement (MCR) reached another important milestone when the final of eight steam generators was lifted into place Saturday (Dec. 18), safely and event-free.

“These new steam generators will be in service for many decades, providing clean, reliable power to Ontario homes and businesses,” said Eric Chassard, Bruce Power’s executive vice-president of projects and engineering. “This is a culmination of many years of hard work and collaboration between Bruce Power and our partners, including SGRT, BWXT, Mammoet, Nuvia and the Building Trades Unions.

“Bruce Power’s ‘Made-in-Ontario’ nuclear supply chain supports Canada’s largest private infrastructure and clean energy project, which injects billions into Ontario’s economy and creates and sustains 22,000 high-skilled jobs annually.” 

Unit 6 contains eight steam generators which are arranged vertically in two columns of four on the east and west sides of the reactor. Each steam generator weighs approximately 320,000 pounds and was lifted through the powerhouse roof enclosure using Mammoet’s PTC-35 crane. This 1,600-ton capacity crane is one of the largest in the world and features a boom the length of a hockey rink that can stretch over the station, which is seven storeys tall, and reach the inner-most steam generators.

The new steam generators were fabricated at BWXT in Cambridge and shipped to site in late 2020. Laser topography was conducted on the steam generators to transform them into a 3D layout to verify dimensions prior to the first lift. These were set in place by Building Trades within a few millimetres’ tolerance.

The Steam Generator Replacement Team (SGRT), a 50/50 joint venture between Aecon and SGT (a partnership between Framatome and United Engineers and Constructors), is Bruce Power’s vendor responsible for replacing the Unit 6 steam generators and was recently awarded a contract for the same scope on Units 3 and 4.

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad