Downtown Kincardine reconstruction project to be tendered this fall

Liz DadsonBy: Liz Dadson  September 4, 2022
Downtown Kincardine reconstruction project to be tendered this fall
Kincardine council has given the green light for a tender to be let this fall, for the $7-million reconstruction project of Queen Street in downtown Kincardine, set to begin next spring.

In committee-of-the-whole Aug. 8, Adam Weishar, director of infrastructure and development, said a working group has been set up to interface with the residents and business community in the affected area.

“The working group has completed a site meeting, reviewed cross-section options, assessed optimal accessibility opportunities, discussed phasing considerations for the proposed works and reviewed a number of elements related to the scope and opportunities to ensure a successful program,” he said. “Additional community outreach and input will be planned as the project advances.”

Weishar added that the working group and the municipal engineer, B.M. Ross and Associates, have put together two cross-sections for consideration: one would resemble the current curb-to-curb street line in Kincardine, and the second, a more recent cross-section that has been used recently in Seaforth, Clinton and Grand Bend.

The second cross-section would add a buffered parking area that is delineated by a secondary curb line. This option would improve the overall accessibility to the existing buildings along Queen, would optically narrow the travelled corridor which would enhance pedestrian safety and further improve the overall function of the street area for events and uses, such as street patios.

Weishar said the working group prefers the second option, including the secondary curb, due to the benefits it provides.

He said the next steps are for council to consider the benefit of tendering this fall, allowing the project to move forward in the spring. He noted that the water and sanitary sewer lines in the area are “on borrowed time” and there is concern that they will fail prematurely.

The 43-week project includes replacement of all water and sanitary services and installation of new storm water services, as well as new sidewalks, curbs, gutters, and paving.

Weishar said the tender would be let this fall, with the results coming to the new council and the project added to the 2023 budget, allowing for the contractor to complete the project during next year’s construction season.

Councillor Laura Haight asked what will happen to the Kincardine Scottish Pipe Band parades next summer, and what will be done with the trees in the downtown core?

Weishar said there have been discussions with the pipe band about a solution for next year. As for the trees, they will be assessed by an arborist as to whether they would survive being transplanted. The working group has agreed with having above-ground planters in the downtown, rather than planting more trees.

“Whatever you have to do to make this a one-year project, that would be great,” said Haight.

“Will borrowing the $7-million impact other capital projects?” asked councillor Dorne Fitzsimmons.

Weishar said the treasurer has stated that external borrowing would be required, but there will be some flexibility with other projects.

Councillor Bill Stewart said he is concerned about borrowing that much when the municipality has already borrowed a lot of money from the water and sewer reserve.

“We’re way behind with our capital projects from 2021,” he said. “Could we push this to 2024?”

Weishar said the downtown core has seen two line breaks already that cost $50,000 each to fix, as well as the hardship for the businesses involved.

“We need to invest in our infrastructure,” he said. “We have to build new and repair the existing lines. And yes, we have a lot of projects on the go, but we have a good start on many of them, with plans in place.”

“Many of these lines were put in 50-60 years ago,” said councillor Dave Cuyler. “They need to be fixed now. I know 43 weeks is a lot of time, but it has to be done and it should all be done at once. We should move ahead with this; tender it in the fall and let the new council make the decision on the project.”

Committee-of-the-whole agreed with the recommendation to grant pre-budget approval for the project to allow tendering of the works this fall, and for the project to be included in the 2023 capital budget. Stewart was the only one opposed.

Council later endorsed that decision, with Stewart opposed.

An open house about this project is slated for Wednesday, Sept. 21, from 6-8 p.m., at the Kincardine Arts Centre, 707 Queen Street, in downtown Kincardine.

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad