​Township awards tender for almost $1-million to fix Bell Bridge on Lake Range Drive

Huron-Kinloss TownshipBy: Huron-Kinloss Township  March 21, 2023
​Township awards tender for almost $1-million to fix Bell Bridge on Lake Range Drive
Huron-Kinloss council has awarded a contract for almost $1-million to rehabilitate structure H38 which is the Bell Bridge on Lake Range Drive, just north of Point Clark.

Public works director John Yungblut brought the tender to council at its meeting Monday night (March 20).

The project will include repairs of the supporting structures, the top deck, and drainage improvements, to extend the life of the bridge. The rehabilitation will require a complete closure of all lanes for 12 weeks, including vehicles, pedestrians, and cyclists.

This bridge repair project was recommended by engineers from B.M. Ross and Associates for rehabilitation within the next five years to preserve the structure. Bell Bridge was built in 1963 and had had some minor maintenance work done in 2011 to clean and re-coat the steel railings.

With the growing lakeshore population, the bridge now incurs traffic numbers of approximately 1,400 vehicles/day in the summer months.

The recommendation to rehabilitate Bell Bridge in 2023 was brought before council by Yungblut at the Feb. 17 meeting.

Due to the relatively high volume of traffic that crosses the bridge on a daily basis and the lengthy detour route that would be required, staff and council explored various options to reduce the impact on the public:
 
  • Full bridge closure for an estimated duration of 12 weeks ($710,000)
  • Staged construction, leaving one lane open, for an estimated duration of 18 weeks ($1.2-million)
  • Hybrid construction, with full closure during structural repairs and one lane open for remainder, for an estimated duration of 15 weeks ($1-million)

At the end of the discussion, council decided to pursue the fully-closed option due to the lowest cost and shortest duration. Two tenders were received, with the lowest bid coming in at $950,000 excluding tax, from AJN Builders.

Monday night, council awarded the project to AJN Builders. Construction is scheduled to begin May 1 and run through July 31, weather permitting.

Full closure of the bridge will require a north detour from Concession 4 to Concession 8 via Highway 21. Council understands that this will be an inconvenience for many residents and visitors; however, it’s important to invest in the municipal infrastructure, including the rehabilitation of the Bell Bridge.



This map indicates the detour out to Highway 21, during the rehabilitation of Bell Bridge on Lake Range Drive in Huron-Kinloss

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad