Bruce County plans to replace Durham Street Bridge in Walkerton

Bruce County communicationsBy: Bruce County communications  June 10, 2023
Bruce County plans to replace Durham Street Bridge in Walkerton
Bruce County is moving forward with plans to replace the Durham Street Bridge which spans the Saugeen River on Bruce County Road 4 in Walkerton. Constructed in 1937, the bridge has served the community for more than 85 years.

Environmental Assessment (EA) work for this project commenced in 2021 and will be completed this year. Bridge construction is scheduled for 2025-26, pending budget approval by county council.

A public meeting was held Oct. 4, 2022, to present project details and receive input from residents and business owners with concerns related to the preferred detour alternative which is to use local municipal roads to detour traffic during the bridge replacement. A second public meeting is tentatively planned for the summer/fall of 2023.

A business information session was held May 11, at the Walkerton Community Centre. Staff from Bruce County Transportation and Environmental Services, B.M. Ross and Associates, the Municipality of Brockton, and the Bruce County Economic Development Department, were present and received feedback. There were many representatives from businesses, as well as residents, who attended the meeting.

The county’s project team provided an update on the Schedule ‘C’ Class EA study of the bridge to the Municipality of Brockton at Tuesday’s council meeting. It was highlighted that an important part of the EA for this project is to consider alternatives and hear feedback from residents, businesses, stakeholders, and municipal partners, which will be shared with county council.

Through the Schedule ‘C’ Class EA, the study is looking at three bridge alternatives:
 
  • Replacement in the same location
  • Repair the existing bridge
  • Do nothing

The preferred alternative at this time, which still needs to be finalized, is replacement in the same location.

Recognizing that the roadway would need to be closed to proceed with bridge replacement, the study went further and looked at four detour alternatives:
 
  • Detour using county roads – north and south routes identified. Truck traffic to be encouraged to use detour.
  • Local detour - using Brockton and county roads with improvements and transit option for pedestrian users. Estimated detour cost: $1.9 million plus engineering.
  • Temporary vehicle bridge - south of the existing bridge, connecting McNab Street and Orange Street. Estimated detour cost: $6.3 million plus engineering.
  • Temporary Pedestrian Bridge - south of the existing bridge, connecting McNab Street and Orange Street. Estimated detour cost: $2.6 million plus engineering.

The approved detour alternative will consider the information received through the EA study which includes consultation with government agencies, Indigenous communities, and interested people, and includes concerns related to the proposed undertaking, analysis of potential environmental effects, and evaluation of the alternatives.

The public is encouraged to comment on the project’s alternatives during this EA period. To date, the project team has received numerous responses from members of the public.

The team is collecting this information and will work to address comments before making a final recommendation for alternatives to county council after the next public meeting in the summer/fall.

Comments can be submitted directly to the project team via E-mail to Kelly Vader, environmental planner at  kvader@bmross.net.

Additional project information can be found on the Bruce County website at www.brucecounty.on.ca/WalkertonBridge.

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad