​Wayne Lowry returns to grade Bell Bridge in Huron-Kinloss, 60 years later

Liz DadsonBy: Liz Dadson  July 12, 2023
​Wayne Lowry returns to grade Bell Bridge in Huron-Kinloss, 60 years later
Wayne Lowry was on the grader when the Bell Bridge was built in 1963, and Monday afternoon, 60 years later, he was back on the grader, smoothing out the gravel before the paving was set to be done later this week.

The 80-year-old resident of Huron-Kinloss Township remembers working on the bridge when it was built.

He was a grader operator for Huron Township (later amalgamated with Lucknow and Kinloss Township to become Huron-Kinloss). Two years later, he became the youngest road superintendent in Ontario at the age of 23.

The Bell Bridge is located on Lake Range Drive, between the 4th Concession and Bell Drive.

This spring, the township included the bridge in its maintenance projects, with work commencing in May and set to be completed at the end of July.

During that time, Lowry, who lives just south of the project, has been driving down in his golf cart to check out the progress every few days. The company doing the work, AJN Builders Inc. of Dublin, asked him to grade the bridge before it’s paved.

As owner of Lowry Construction since 1970, he knows his way around heavy equipment and still grades laneways and other projects for people. His son, Greg, is now operating the construction business, while his grandson, Liam, works the farming end of things.

Lowry was pleased to be on the grader Monday afternoon as the company was finishing the waterproofing work on the bridge deck which involved the application of tar and a protective coating. He expects if it doesn’t rain, the paving could be done Thursday or Friday.

The bridge project included repairs of the supporting structures, the top deck, and drainage improvements to extend the life of the structure. The rehabilitation work required the complete closure of the bridge for 12 weeks, including vehicles, pedestrians, and cyclists.

This project was recommended by engineers from B.M. Ross and Associates for rehabilitation within the next five years to preserve the structure. The Bell Bridge had some minor maintenance work done in 2011 to clean and re-coat the steel railings. With the growing lakeshore population, the bridge now incurs traffic numbers of approximately 1,400 vehicles/day in the summer months.

The township expects the bridge will be completed and the road re-opened ahead of schedule.

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad