Bruce Power contracts major industry suppliers for steam generator replacement project

Liz DadsonBy: Liz Dadson  March 18, 2018
Bruce Power contracts major industry suppliers for steam generator replacement project
The signing of a major agreement for the replacement of steam generators at the Bruce Nuclear site, was completed Friday morning, after it was postponed in December, due to a snowstorm.

Representatives of a fully-integrated joint venture formed among AECOM, Aecon and Framatome (formerly AREVA) – the Steam Generator Replacement Team (SGRT) - joined Bruce Power at the Framatome warehouse on Highway 21, to sign the contract, valued at more than $130-million to replace steam generators at Unit 6.

Work is scheduled to reach substantial completion in the first quarter of 2022. In addition to the contract for Unit 6, SGRT signed a long-term preferred supplier agreement, with a firm pricing structure, for steam generator replacements at the plant’s remaining five units as part of the Major Component Replacement (MCR) project. This agreement, with provisions for a long-term partnership through 2032, gives Bruce Power the benefit of experience and relationships of multiple projects, and allows SGRT to establish a long-term presence in the Bruce Power community.

“Replacement of steam generators is a key part of the MCR project,” said Mike Rencheck, president and chief executive officer of Bruce Power. “We have established an agreement for the Unit 6 steam generator replacement to start, and to establish a firm path for steam generator replacements in our subsequent five units, securing both resources and estimates for future work.

“Partnerships, like this one, set up our Life-Extension Program for success by bringing certainty, innovation and technology, which are critical in building a high-performing team that is prepared to deliver projects on-time and on-budget.”



Holding the plaque, representing the signing of a contract for steam generator replacement on Bruce Power's MCR project, are Mike Rencheck (left), president and CEO of Bruce Power, and SGRT partners John Beck of Aecon, Gary Mignogna of Framatome, and Robert LoCurto of SGT, Friday morning in Kincardine

“We are proud to serve as a long-term strategic partner with Bruce Power to support its MCR project,” said Robert J. LoCurto, president of SGT, a company co-owned by Framatome and AECOM, and chairman of the SGRT executive committee.

“SGRT provides the depth and experience of Aecon in Canadian nuclear projects with SGT’s experience with steam generator replacement and the resources of AECOM and Framatome. With our team based in Kincardine, we are committed to developing our workforce locally and becoming an integral part of the community.”

He noted that the team began engineering design for the refurbishment of Unit 6, back in March, 2017. “Yesterday (March 15), we hit a milestone with completion of the design change package. Now, we can begin the engineering construction planning.”

John Beck, president and chief executive officer of Aecon, said he and his company are looking forward to playing a key role in the delivery of this program.

“We have worked on the Bruce site since the original Bruce A and Bruce B new build,” he said, “as well as the Bruce Heavy Water Plant installation, and more recently, the refurbishment of Units 1 and 2. We're here for the long-term.”

He said several of Aecon's leaders will be relocating to Bruce County and opening offices locally.

Gary Mignogna, president and chief executive officer of Framatome, which reverted back to its original name from AREVA in January, thanked the SGRT partners for showing their confidence in his company.

“We've been working on steam generator replacement since 1984,” he said, “and we've replaced a total of 70 steam generators. We are absolutely committed to this area. We do high-voltage work for Bruce Power; we are working to commercialize medical isotopes; and we want to increase employment in the region.”

Rencheck welcomed each of the companies participating in the agreement-signing, and thanked the group for headquartering the joint venture here.

“It's exciting to have three great international companies moving into our community,” he said, “to help Bruce Power in the near-term and in the long-term. As we see it, the plant supports the community, and the community supports the plant. We are proud to welcome SGRT as part of this community.”

He said the steam generator replacement contract for Unit 6 is valued at $130-million, and then based on performance, the entire contract for the MCR project is valued at $800-million.



Mike Rencheck (right), president and CEO of Bruce Power, is joined by the SGRT partners in signing the major agreement for steam generator replacement: John Beck (left), president and CEO of Aecon; Gary Mignogna, president and CEO of Framatome; and Robert LoCurto, president of SGT, a company co-owned by Framatome and AECOM, and chairman of the SGRT executive committee; Friday morning in Kincardine

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad