Huron-Kinloss okays almost $100,000 to protect Point Clark Lighthouse parking lot

Huron-Kinloss council has granted pre-budget approval to spend up to $95,850, plus tax, on protecting the south end of the Point Clark Lighthouse parking lot.
At the committee-of-the-whole meeting Jan. 13, community services director Mike Fair explained that the increased lake level last year caused significant erosion at the parking lot beside the lighthouse and the harbour wall. Staff directed contractors to place stone for a temporary measure to protect the southeast parking lot until a permanent solution could be found.
Since October, 2019, the increased lake level and the November gales have resulted in several high-wave-action events that have further eroded the shoreline adjacent to the parking lot, in addition to eroding a portion of the existing harbour wall at the south side of the parking lot, said Fair.
“The Point Clark Boat Club has met with township staff several times to discuss the high lake level and the effect on the exterior harbour walls,” said Fair. “The boat club will be meeting with its membership in the spring to discuss the remaining harbour wall conditions.”
The high water level of Lake Huron and heavy wave action, are eroding the area at the south end of the Point Clark Lighthouse parking lot, and the harbour wall; photo courtesy of Huron-Kinloss Township
Engineer Dale Erb of B.M. Ross and Associates, stated in a report that the best remediation is armour stone along the existing shoreline, similar to what Kincardine did along the lakeshore, north of the Kincardine Harbour.
As for the harbour wall, Erb agreed with the township that the berm must be raised, using armour stone and filter stone, laid on top of new geotextile filter. “Where the elevated berm will be prone to wave action, three to four tonne of armour stone would be appropriate. Smaller filter stone can be used to protect the areas that are currently eroding behind the existing rock. It is important that geotextile be used under all new rock to protect against the migration of materials through the stone.”
Fair said he received two quotes for supply and installation of 107 feet of armour stone – one from Elliott Construction, $74,750; and the other from Kempton Construction, $58,850.00. An additional $40,000 would cover the cost of fortifying 95 feet along the south section of the parking lot, using the existing temporary stone.
Permits are required from the Ontario Ministry of Natural Resources and Forestry, said Fair. “Due to the nature of the work, proximity to the shoreline, and possible higher lake levels in 2020, it is recommended that the work be completed in February or March while the shoreline is frozen and wave wash is not a factor. Staff would require pre-budget approval in order to expedite the project upon permit approvals.”
Council approved the lakeshore remediation plan, and granted pre-budget approval for the cost.